Construction Scheduling Services and CPM Schedules Built to Your Contract
After award, we build the CPM schedule your contract actually asks for: baseline, monthly updates with a narrative, look-aheads your superintendent will use, and fragnets when the job slips. Native P6, Microsoft Project or Asta files come back with a readable PDF Gantt.
What ships with every schedule
- The native file, XER, XML, MPP or Asta, yours to update
- A readable PDF Gantt, and a plot-size layout on request
- Basis of schedule narrative: crews, rates, calendars
- Two-step check: a self-check, then an independent second pass
- A clause by clause spec matrix with every baseline built to an agency spec
The schedule document ladder, from the proposal schedule to baseline schedule development to as-built
Your contract names five or six schedules, each with its own due date and acceptance rule, and CPM scheduling services that ignore the difference collect comments on all of them.
Before award, and the first three weeks after NTP
The proposal or bid schedule
PRE-AWARDA logic sketch of twenty to sixty activities that shows a selection committee you understand the sequence. Nobody accepts it as a baseline and no update runs against it.
Outsourced bid management servicesThe preliminary schedule
NTP TO NTP+21Due within days of notice to proceed, covering the first 60 to 90 days in detail plus the milestone spine, so your first pay application is not hostage to a baseline still in review.
Baseline schedule development, the update chain behind it, and as-built
The initial or baseline schedule
THE CONTRACT DOCUMENTFull logic, every activity coded, calendars set, durations defended in the narrative, typically due 30 to 60 days after NTP. Acceptance is not approval: most specifications say the owner takes it without adopting your means and methods.
What we will not promise you
That your owner accepts it first pass. Nobody honest promises that. What we commit to: comments on scope we scheduled get a resubmittal at no charge, and you get in writing which are scope changes and which are ours.
Periodic updates
MONTHLY, USUALLYActual starts, actual finishes, remaining durations and a data date, on the cycle the specification names. Each is a dated snapshot, and the snapshots are the evidence.
See the monthly cycleThe revised baseline
WHEN THE PLAN CHANGESNot a monthly event. It belongs to a change in the work, an accepted time extension, or a sequence that is dead. Re-baselining to make slippage disappear erases the variance record you will want later.
The as-built schedule
AT CLOSEOUTEvery activity carrying its real start and finish, assembled from the update chain if it was kept and reconstructed from daily reports and pay applications if it was not. The second route is the expensive one.
Baseline rejected by your owner? Send the file before you resubmit
Send the schedule and the comment log. You get the metric counts, which comments are defects and which are scope, and a straight answer on what a resubmittal takes.
What we need from you before a single activity is typed
A scheduler who starts typing before this list is answered produces a bar chart, not a schedule.
Start with the paper. The schedule specification section, whether it is 01 32 16 or an agency number, sets the software, the submission dates, the coding, the level of detail, the narrative content and the float ownership clause. Half the rejection list disappears when somebody reads that section first.
Then the person who is going to build it. We book a working call of about an hour with your superintendent, covering sequencing, crew sizes, planned shifts, laydown and crane constraints, and the shutdown windows nobody wrote down. If your superintendent will not give us that call, say so at quote stage rather than after delivery. We can still build a compliant, well-formed file off the drawings and the contract, but it will not match how your crews work.
Who owns the float, in the schedule we build
Float is a project asset three parties each believe belongs to them, and your contract has a clause about it that nobody on your team has read.
Who owns the float in a construction schedule?
Whoever your contract says. Three positions exist: contractor owned, owner owned, and project owned on a first come first served basis. Where the contract is silent, US practice treats float as a shared project resource. Find the clause before the baseline is built.
What does negative float actually mean?
That the calculated finish is later than the date you are contractually held to, by that many days. It is not an error: it is the file telling you the plan misses the date, and honest negative float is the strongest support a time extension request can have.
Can I protect float without hiding it?
Yes, and the visible method is the only one that survives review. Put the buffer where it belongs, as a named, coded activity ahead of the milestone it protects. What does not survive is padded durations or dropped-in constraints, because a reviewer counts both.
Where a defensible duration comes from, quantities, crews and production rates
Ask three schedulers where a 15 day duration came from and two will answer experience. Here is the arithmetic that answers an owner challenge.
Take the quantity off the drawings, not off the last job
Name the crew you will actually field
Apply a production rate you can name the source of
Reconcile the total hours against the priced estimate
Resource and cost loading, tied to the schedule of values
A resource loaded schedule in Primavera P6 and a cost loaded schedule driven off your schedule of values are two jobs on one file.
| Labor hours | Crew hours per activity, off the estimate | Manpower histogram and leveling | A 42 man week you cannot staff |
|---|---|---|---|
| Activity cost | Your schedule of values, split down | The basis of the monthly pay app | SOV lines that map to no activity |
| Mobilization | Schedule of values, line one | Watched closely for front loading | Cash pulled forward into month one |
| Physical percent | Installed quantity over total quantity | Earned value and the S-curve | Percent read off the calendar instead |
The monthly update cycle, timed to your pay application
The update is the only contemporaneous record of what happened and when, and it is what a time extension request gets built out of eighteen months later.
Day 20 to 22: the data date is set and published
Day 22 to 24: field status comes back on one form
Day 24 to 26: the file is statused and recalculated
Day 26: the monthly schedule update and narrative report
Day 27 to 28: the independent check, then it ships
Ask a scheduler about your spec before you commit to anything
Float ownership, a submission date you cannot make, whether the spec really requires a cost loaded file. Put it to a scheduler and get a direct answer.
Time impact and windows analysis, and what the updates have to carry
Time impact analysis is not a document written after the fact. It is a calculation run on a schedule already being maintained, which is why the update cycle matters more than the method.
The main methods, and when each one is the right one
AACE 29R-03 sorts these into observational and modeled.
As-planned versus as-built
OBSERVATIONALThe baseline laid against what actually happened, period by period. Readable by non-schedulers, weak wherever there is concurrency.
Windows or contemporaneous period analysis
OBSERVATIONALThe job cut into periods at the monthly updates, with the driving path recalculated inside each one. If the updates were never produced, it is unavailable to you.
Time impact analysis by fragnet insertion
MODELED, PROSPECTIVEA fragnet, the small network representing the change, inserted into the accepted update immediately before the event and recalculated. The movement in the completion date is the time impact.
Schedule delay analysis services, and the line we do not cross
What we prepare
DOCUMENTATION SUPPORTThe fragnet and its insertion at the correct data date. The windows analysis off your update chain. The as-built reconstruction. The exhibits and narrative chronology, in a form your counsel can work from.
What we do not do
THE BOUNDARYWe do not testify. We do not issue sealed opinions, and nobody here holds a professional engineering license to seal one with. We do not opine on entitlement, give legal readings of your contract, or choose your means and methods.
Send every schedule specification at once, one fixed quote per job
Each job is read on its own documents and gets its own fixed quote and delivery date in writing, and a scope change comes back as a revised quote. A monthly partnership keeps the update cycles of several jobs in one queue.
CPM scheduling services to agency specifications, and the compliance matrix that answers them
Federal and DOT schedule specifications prescribe coding, level of detail, submission format and payment linkage, not a bar chart. Every baseline built to one of them ships with a clause by clause matrix mapping the spec to the deliverable.
| UFGS 01 32 01.00 10 | A P6 network, prescribed coding, narrative, monthly update | Native XER with the coding dictionary applied |
|---|---|---|
| SDEF export | A fixed format activity file the agency loads on its side | SDEF exported from P6 with the coded fields populated |
| Activity coding dictionary | Responsibility, feature of work, area, phase, bid item | Codes applied while building, not retrofitted after review |
| Level of detail | Activity durations capped, often at 20 working days | Durations sized to the update period, listed in narrative |
| Cost loading | Every activity carrying value, summing to the contract | Loaded off your schedule of values, reconciled to the total |
| State DOT CPM provisions | Bid item numbers as activity codes, letting specific dates | Activity codes mapped to your own bid item numbers |
Questions about our construction scheduling services, answered straight
What contractors ask a construction schedule consultant before they send anything over.
Cost and timing
Float and logic
When it goes wrong
Files and specifications
Hire a CPM scheduler
for one schedule or for every job
Send the schedule specification section, your contract dates and the current drawing set. A scheduler reads it, quotes it in writing with a delivery date, and nothing is invoiced until you approve that number.